(COBIE-ER-05) Exchange Project Handover - Asset Location
Added by Bill East, last edited by Bill East on May 02, 2007  (view change)
Labels: 
(None)


(COBIE-ER-05) Exchange Project Handover - Asset Location

NBIMS Development Stage

Stage Name Status
0 Draft, not yet approved as NBIMS project  
1 Part of a 'pilot' project  
3 Part of a project out for 'consensus' review
4 Part of an operational standard  
5 Superseded by:  
6 Retired  

Note: For information on the specific stages of NBIMS project development, please visit www.nbims.org.

Project Stage

Stage Name Valid
0 Portfolio requirements  
1 Conception of need  
2 Outline feasibility  
3 Substantive feasibility  
4 Outline conceptual design  
5 Full conceptual design  
6 Coordinated design and procurement  
7 Production information  
8 Construction
9 Operation and maintenance
10 Disposal  

Note: While the information exchange described in the COBIE project occurs following construction during building handover, as noted in the table above, the data contained in this particular exchange requirements is generally applicable throughout the facility life-cycle.

Overview

COBIE contains information information describing the operations, maintenance, and assets in capital facilities. The authoritative sources for this information include designers, builders, installers, and manufacturers. On the design side of the exchange, BIM-based design tools may be used to capture COBIE data. From construction, information about approved submittals are included in COBIE exchanges. Builders identify products to be installed. Manufacturers provide operating and maintenance information. Installers provide serial and tag numbers. Quality Control/Assurance staff provide test and certification reports. All these parties can capture building handover data through the COBIE standard, tying their diverse set of software together for the purpose of providing a consistent data set of operations, maintenance, and asset management to building staff.

This exchange requirement defines the location of specifically named building components needed for construction-operation information handover. The information contained in this exchange requirement is commonly found in a variety of "schedules" found on typical U.S. construction design drawings. A commonly identified individual components are found in the mechanical system, for example "AHU-1" or "Pump 5". An example scenario for this information is shown in the table below.

Task Scenario
Component Name Identifies the type of product that should be installed in the facility.
Asset Class (Reference) Reference to the asset class that contains the overall information about the product. The asset class is identified in the submittal register.
Space (Reference) Reference to the lowest leaf(s) of the space hierarchy applicable for the type of product.

The information provided through this information exchange should be a subset of information that already exists in the design building information model, as appended/changed during construction. Information related to the facility that may be exchanged include:

  • All individually named products must be referenced to a specific material, product, or equipment class
  • All individually named products and equipment installed int the building must be explicitly identified.
  • All individually named products and equipment must be referenced to their designed (or later) installed space reference.

The following information auditing is also required for all COBIE file exchanges that occur in a batch file transfer mode. Software that mediates that transmission of COBIE data may capture this data automatically based on process model implementations:

  • The party who created the data provided. This is required for individual record.
  • The full history of all changes to the data must be included in the data file.

The authoritative source for this information is the design building information model. Ideally the information in this project wrapper will have been created during early design and "handed down" with the project as work progressed from design through to construction.

Information Requirements

Context Information Needed MAN REC OPT Actor Supplying Functional Part
Precursor Space Name for each space must be identified before it can be associated with specific materials, products, and equipment.     Designer or Constructor fp_model_space
Precursor Product Name for each material, product, or equipment to installed in the facility must be identified before specific components can be associated with those types.     Designer or Constructor fp_model_inventory(asset)
Component Name Identify the name of the individually named material, product, or equipment to be installed in the facility. An example of component names would include "AHU-1" or electrical panel "P-1"     Designer or Constructor fp_model_asset
Authoritative Source The user responsible for creating the project wrapper data set.     Designer or Constructor fp_apply_owner_history
History All versions of information captured during the project will be provided in the file. Superseding data is explicitly identified.     Designer or Constructor fp_apply_owner_history