Log In   View a printable version of the current page.
2 - Result - Exchange HVAC Model - Equipment (ER)
Added by Brendan McFarlane, last edited by Brendan McFarlane on Sep 06, 2006  (view change)
Labels: 
(None)


HVAC Equipment Exchange Results for Piping Designer

Building model updated for component information providing information to the Piping Designer. Piped Services requirements of components may have been provided previously or may be specified through this exchange requirement.

Project Stage - Scheme Design

The following exchange requirements apply to the scheme design stage of a project

Type Information Provided Actor Receiving Man Opt Functional Part
Model An HVAC Equipment item shall be assigned a locally unique identifier. it is identified as recommended throughout all project stages within this exchange requirement. Piping Design   HVAC Equipment Identifier (FP)
Model An HVAC Equipment shall be assigned to a type classification. This identifies what type of equipment the exchange refers to - for example Air Handling Unit, External Louvre, Fan, Duct System, Silencer etc... Piping Design   HVAC Equipment Classification (FP)
Model HVAC Equipment physical shape and size. The model should include details of the actual or proposed physical dimensions of the equipment, dependent on the stage of the project. During the early stages of the design this information may only be used for establishing the requirements of the service spaces and maintenance access for the project. Piping Design   HVAC Equipment Dimensions (FP)
Model HVAC Equipment location. The model should include details of the actual or proposed physical location of the equipment, dependent on the stage of the project. Piping Design   HVAC Equipment Location (FP)
Model HVAC Equipment Piping Load provision, which defines the characteristics of a piping connection load associated with a piece of HVAC equipment that needs to be satisfied by the piping system. Information required includes the piping medium (e.g. low temperature hot water, chilled water, steam, drain), and the required flow rate and energy load of the service, pressure drop etc.. are defined here. During the early stages of the design this information may only be used for establishing the estimated requirements of the piping system for the project. Piping Design   HVAC Equipment Piping Load (FP)
Model HVAC Equipment Piping Interface provision, which defines the details of a piping connection interface associated with a piece of HVAC equipment that needs to be satisfied by the piping system. Information required includes the location, size and type of connection (e,g, flange, union, screwed etc...), material and specification of the required connection (e.g. stainless steel PN16 flange) are defined here. During the early stages of the design this information may only be used for establishing the estimated requirements of the piping system for the project. Piping Design   HVAC Equipment Piping Interface (FP)

Project Stage - Detailed Design

The following exchange requirements apply to the scheme design stage of a project

Type Information Provided Actor Receiving Man Opt Functional Part
Model An HVAC Equipment item shall be assigned a locally unique identifier. it is identified as recommended throughout all project stages within this exchange requirement. Piping Design   HVAC Equipment Identifier (FP)
Model An HVAC Equipment shall be assigned to a type classification. This identifies what type of equipment the exchange refers to - for example Air Handling Unit, External Louvre, Fan, Duct System, Silencer etc... Piping Design   HVAC Equipment Classification (FP)
Model HVAC Equipment physical shape and size. The model should include details of the actual or proposed physical dimensions of the equipment, dependent on the stage of the project. During the early stages of the design this information may only be used for establishing the requirements of the service spaces and maintenance access for the project. Piping Design   HVAC Equipment Dimensions (FP)
Model HVAC Equipment location. The model should include details of the actual or proposed physical location of the equipment, dependent on the stage of the project. Piping Design   HVAC Equipment Location (FP)
Model HVAC Equipment Piping Load provision, which defines the characteristics of a piping connection load associated with a piece of HVAC equipment that needs to be satisfied by the piping system. Information required includes the piping medium (e.g. low temperature hot water, chilled water, steam, drain), and the required flow rate and energy load of the service, pressure drop etc.. are defined here. During the early stages of the design this information may only be used for establishing the estimated requirements of the piping system for the project. Piping Design   HVAC Equipment Piping Load (FP)
Model HVAC Equipment Piping Interface provision, which defines the details of a piping connection interface associated with a piece of HVAC equipment that needs to be satisfied by the piping system. Information required includes the location, size and type of connection (e,g, flange, union, screwed etc...), material and specification of the required connection (e.g. stainless steel PN16 flange) are defined here. During the early stages of the design this information may only be used for establishing the estimated requirements of the piping system for the project. Piping Design   HVAC Equipment Piping Interface (FP)

Project Stage - Construction Design

The following exchange requirements apply to the Construction design stage of a project

Type Information Provided Actor Receiving Man Opt Functional Part
Model An HVAC Equipment item shall be assigned a locally unique identifier. it is identified as recommended throughout all project stages within this exchange requirement. Piping Design   HVAC Equipment Identifier (FP)
Model An HVAC Equipment shall be assigned to a type classification. This identifies what type of equipment the exchange refers to - for example Air Handling Unit, External Louvre, Fan, Duct System, Silencer etc... Piping Design   HVAC Equipment Classification (FP)
Model HVAC Equipment physical shape and size. The model should include details of the actual or proposed physical dimensions of the equipment, dependent on the stage of the project. During the early stages of the design this information may only be used for establishing the requirements of the service spaces and maintenance access for the project. Piping Design   HVAC Equipment Dimensions (FP)
Model HVAC Equipment location. The model should include details of the actual or proposed physical location of the equipment, dependent on the stage of the project. Piping Design   HVAC Equipment Location (FP)
Model HVAC Equipment Piping Load provision, which defines the characteristics of a piping connection load associated with a piece of HVAC equipment that needs to be satisfied by the piping system. Information required includes the piping medium (e.g. low temperature hot water, chilled water, steam, drain), and the required flow rate and energy load of the service, pressure drop etc.. are defined here. During the early stages of the design this information may only be used for establishing the estimated requirements of the piping system for the project. Piping Design   HVAC Equipment Piping Load (FP)
Model HVAC Equipment Piping Interface provision, which defines the details of a piping connection interface associated with a piece of HVAC equipment that needs to be satisfied by the piping system. Information required includes the location, size and type of connection (e,g, flange, union, screwed etc...), material and specification of the required connection (e.g. stainless steel PN16 flange) are defined here. During the early stages of the design this information may only be used for establishing the estimated requirements of the piping system for the project. Piping Design   HVAC Equipment Piping Interface (FP)

Powered by Atlassian Confluence, the Enterprise Wiki. (Version: 2.1.3 Build:#408 Jan 23, 2006) - Bug/feature request - Contact Administrators